C-65.1, r. 8.01 - Pilot project to facilitate payment to enterprises that are parties to public construction work contracts and related public subcontracts

Full text
16. Any subsequent payment owing by a subcontractor to another subcontractor must be made on or before the 10th day of the month, the 15th day of the month and so on to the end of the subcontracting chain.
M.O. 2018-01, s. 16.
In force: 2018-08-02
16. Any subsequent payment owing by a subcontractor to another subcontractor must be made on or before the 10th day of the month, the 15th day of the month and so on to the end of the subcontracting chain.
M.O. 2018-01, s. 16.